Construction Update Gig Harbor MATTERS UPDATED: 12-29-08
AUSTIN STREET PROJECT -- UPDATED: 12-29-08
Project Description: The City's Austin
Street project is intended to improve Austin Street in anticipation of the
temporary road closure of Harborview Drive as part of the forthcoming
Wastewater Treatment Plant Expansion project. This project will
consist of removing and relocating the sidewalks at the intersection of
North Harborview Drive and Austin Street along with pavement repair along
Austin St.
Anticipated Work Schedule:
The City awarded the construction contract at the December
8th City Council meeting to Riverton Contractors, Inc.
Due to the holidays and weather conditions, the project will start during
the first or second week of January 2009. The project has a schedule
of 15 working days and an anticipated completion date of the first week in
February. During
construction, daily access to Austin Street will be restricted, and full
roadway closures may occur on a limited basis.
Primary project contact:
Amy Londgren, Project Manager at (253) 853-7662 or by e-mail at
londgrena@cityofgigharbor.net
BURNHAM / BORGEN / SR-16 (BB-16) INTERCHANGE OPTIONS UPDATE -- City Council Selects Preferred Alternative click here.....
Over the
past year, a great deal of work and analysis has been done to develop a
long-term solution for traffic management at the Burnham / Borgen / SR-16
(BB-16) Interchange. The City of Gig Harbor has identified three
construction options (click here to view), all of which will have
significant traffic and economic impacts to the region.
For more information, contact Project Engineer,
Marcos McGraw at 253 851-6170. To see larger images, go back to the
City's Home Page under "What's New" and click on BB-16 Interchange
Information.
CANTERWOOD BOULEVARD RE-OPENED ON NOVEMBER 26th -- UPDATED: 12-29-08
Canterwood Boulevard is open to public travel, but all project work will not
be complete until January 2009.
The street will remain open in the temporary lane configuration for
approximately two months. The current speed limit on the street is 25 MPH.
Intermittent disruptions should be expected until all project
work is completed.
Work in Progress: The
contractor is unable to perform any work this week due to the snow and cold
temperatures. The temporary traffic devices on Canterwood Boulevard
will remain through the end of the year. The State Department of
Transportation will be working along the shoulders of the roundabouts with
small drilling machines to investigate soil conditions for walls. This
work is anticipated during the first couple of weeks in January 2009 and may
cause some disruption to traffic flows.
Primary
project contact:
Marcos
McGraw, Project Engineer at (253) 8532647 or by e-mail at
mcgrawm@cityofgigharbor.net
Why
was Canterwood closed during construction? (PowerPoint)
CUSHMAN TRAIL PROJECT -- UPDATED: 12-12-08
Phase 2 of the Cushman Trail is
a project partnership with Pierce County, Tacoma Public Utilities and the
City of Gig Harbor.
Project Description:
Phase 2 of the Cushman Trail is a project in partnership with Pierce County,
Tacoma Public Utilities and the City of Gig Harbor. The new trail extension
will be 2 ˝ miles of 16 foot wide pervious asphalt trail with gravel
shoulders on each side. This phase connects to the existing trail at the
Pierce Transit Park & Ride on Kimball Drive and will end at 96th
Street NW (off Burnham Drive). A new trailhead with restrooms and
parking will be located at the end of Grandview Street. New crosswalks will
be installed across Grandview, Foster and Rosedale Streets. The trail has a
section between Foster Street and the Wilkinson Farm Park that will be built
on a pin-pile bridge to minimize impacts to the wetland.
Work Completed:
Surveying, clearing, grubbing and erosion control for the trail began on
9/15/08. Contractor is completing prep work for walls and culverts and will
be realigning a portion of a water main to cross a section of the pin-pile
bridge. Gabion
basket walls have been installed.
Anticipated Work Schedule:
Winter schedule will begin approximately the week of December 22nd. The winter schedule will include less work with large equipment to reduce
the risk of erosion and excessive disruption of wet, native soils. Work not
requiring heavy equipment will continue – moving sections of water main,
placement of ‘pin piles’ and maintaining erosion control throughout the
project.
All work is scheduled to be complete by early summer 2009.
Primary project contact: Marcos
McGraw, Project Engineer at (253) 8532647 or by e-mail at
mcgrawm@cityofgigharbor.net
HARBORVIEW DRIVE PROJECT UPDATE --
UPDATED: 12-29-08
Project Description:
The City’s Harborview Drive Project is intended to repair a small section of
roadway along Harborview Drive where a February 2008 water main break
buckled the road surface. This repair is located adjacent to Murphy’s
Landing Marina between Stinson Avenue and North Harborview Drive. The
Harborview Drive Project will consist of removing the existing road surface
and replacement with new asphalt pavement.
Anticipated Work Schedule:
The City recently awarded the contract for this work at the December 8th
City Council meeting to Riverton Contractors, Inc. Due to the holidays
and weather conditions, the project will start during the first or second
week of January 2009. The project has a schedule of 15 working days
and an anticipated completion date of the first week in February. During
construction, daily access through this area along Harborview Drive may be
limited by lane closures at times. However, traffic control will be
provided while construction activities are occurring.
Primary project contact:
Amy Londgren, Project Manager at (253) 853-7662 or by e-mail at
londgrena@cityofgigharbor.net
KENNETH LEO MARVIN VETERANS MEMORIAL PARK PROJECT -- UPDATED: 11-21-08
This 6.76 acre site was purchased by the City of Gig Harbor in order to
provide a neighborhood park facility on the west side of Gig Harbor. A
restroom facility and covered picnic shelter area will be constructed in
2009.
This project includes road improvements to 50th Street in front of and
adjoining the park.
Click here for current project update
click here for map of
vicinity.
WASTEWATER TREATMENT PLANT EXPANSION PROJECT - ROAD CLOSURE NOTICE -- UPDATED:
12-04-08
In order to begin construction of the Wastewater
Treatment Plant Expansion Project, Harborview Drive will be closed from
North Harborview Drive (at Le Bistro Restaurant) to Austin Street. The ROAD
CLOSURE will be in effect from approximately March 2009 to March 2010
(estimated 12 months). In anticipation of the Harborview Drive road
closure, roadway improvements to Austin Street will include repair of the
roadway surface and modifications at the intersection of Austin Street and
North Harborview Drive to provide improved vehicle access. Please check this website for periodic updates, as
changes may occur. For more information, contact Jeff Langhelm, Sr.
Engineer at (253) 853-7630 or by e-mail at
langhelmj@cityofgigharbor.net.
Click here for map.
Gig
Harbor North Area Roundabouts
For more information on driving the newly
re-striped roundabouts, please click on our new
ROUNDABOUT DRIVING INFORMATION
link:
roundabout channelization
10-07.pdf that
is also listed on the City of Gig Harbor Homepage under
"WHAT'S NEW"
We thank you for your support during these construction improvements. If you have any questions, please contact the Public Works Engineering Department at 851-6170.
"We're all in this together!"
Watch the Peninsula Gateway and this website
for updated information.